S.NoPublish Date End DateView
Supply and Installation of Wooden Partitions, Glass Doors, Reception Counter and Renovation of office wash room at M-3 Industrial City (SEZ), Faisalabad26 Apr 202106 May 2021Evaluation Report
Engineering Consultants’ Services (Electrical) towards Installation of an additional transformer of capacity 31.5/40MVA at 132kV Grid Station No. 02 at M-3 Industrial City, near Sahianwala Interchange, M-4 Motorway, Faisalabad
Procurement No. Consult-16
05 July 202116 July 2021ER Consult-16
Engineering Consultants’ Services (Electrical) towards Installation of an additional transformer of capacity 20/26MVA at 132kV Grid Station No. 01 at Allama Iqbal Industrial City, near Sahianwala Interchange, M-4 Motorway, Faisalabad
Procurement No. Consult-17
05 July 202116 July 2021ER Consult-17
Engineering Consultants’ Services (Electrical) for Design as per well-established practices and standards of NTDC/FESCO (WAPDA) and Construction Supervision for 132kV Grid Station No. 03 with two Nos. 31.5/40MVA power transformers, at M-3 Industrial City, near Sahianwala Interchange, M-4 Motorway, Faisalabad.
Procurement No. Consult-18
05 July 202116 July 2021ER Consult-18
Construction of Wet Well & Dry Well and Sewer Lines Crossing under Railway Line in Phase-II at M-3 Industrial City, Near Sahianwala Interchange M-4 Motorway, Faisalabad;
Contract No. FIC-053

19 July 202129 July 20212021-0705-O3-F73 (FIC-053 Financial BER)
Construction of Road along Seam Nala at Allama Iqbal Industrial City, Near Sahianwala Interchange M- 4 Motorway, Faisalabad - AIIC-00216 Sep 202126 Sep 2021Evaluation Report -- AIIC-002
COMMISSIONING AND ALLIED CIVIL WORKS FOR THE CONSTRUCTION OF NEW 132KV GRID STATION NO. 03, WITH TWO NO(S). 31.5/40M8 March 202218 March 2022FIEDMC - Financial Evaluation Report GS - 03
COMMISSIONING AND ASSOCIATED CIVIL WORKS FOR ADDITION OF ONE NUMBER 132/11.5 kV, 31.5/40 MVAPOWER TRANSFORMER AT 132k8 March 202218 March 2022FIEDMC - Financial Evaluation report GS - 02
COMMISSIONING AND ALLIED CIVIL WORKS FOR ADDITION OF ONE NUMBER 132/11.5 kV, 20/26MVA POWER TRANSFORMER AT 132KV AIS SUB STATION NO. 1 ALLA8 March 202218 March 2022FIEDMC - Financial Evaluation Report GS - 01
Hiring of Security Services Company Evaluation of Financial Proposals 13 May 202223 May 2022Evaluation report